Highway 417 EB off Ramp to Bronson Avenue

  • Closed for 2 weekends in 2022 for the EBL approach slab construction staging at Rochester Street and Booth Street.
  • Six (6) month closure in 2023 for retaining wall work and Percy Street bridge replacement work.
  • Closed for 2 weekends in 2023 for the EBL approach slab construction staging at Bronson Avenue and Percy Street.

Highway 417 off Ramp WB to Kent Street

  • Four (4) month closure in 2023 for storm sewer and retaining wall work.

Highway 417 WB off ramp to Bronson Avenue

  • Closed for 3 weeks in 2023 for the Bronson Avenue bridge replacement work.
  • Closed for 3 weekends in 2023 for the WBL approach slab construction staging at Bronson Avenue and Percy Street.

Bronson Avenue on Ramp to Highway 417 WB

  • Four (4) month closure in 2022 for retaining wall work.
  • Closed for 3 weekends in 2022 for the WBL approach slab construction staging at Rochester Street and Booth Street.
  • Closed for 2 weekends in 2024 for the WBL approach slab construction staging at Preston Street.
  • Closed for the duration of the Highway 417 full closure for 3 rapid bridge replacements.

Rochester Street on Ramp to Highway 417 WB

  • Closed for 3 weeks in 2022 for the Rochester Street bridge replacement work.
  • Closed for 1 weekend in 2022 for the WBL approach slab construction staging at Rochester Street and Booth Street.
  • One (1) month closure in 2023 for pre-work at Preston Street bridge.
  • Four (4) month closure in 2024 for the Preston Street bridge replacement work.

Highway 417 WB off Ramp to Rochester Street

  • Closed for 3 weeks in 2022 for the Rochester Street bridge replacement work.
  • Closed for 2 weekends in 2022 for the EBL approach slab construction staging at Rochester Street and Booth Street.
  • Four (4) month closure in 2024 for the Preston Street bridge replacement work.

Highway 417 EB off Ramp to Parkdale Avenue

Three (3) month closure in 2024 for retaining wall work.

Parkdale Avenue on Ramp to Highway 417 EB

  • Closed for the duration of the Highway 417 full closure for each RBR; a total of 5 occurrences.
  • Closed for 2 weekends in 2022 for the EBL approach slab construction staging at Rochester Street and Booth Street.
  • Closed for 2 weekends in 2023 for the EBL approach slab construction staging at Bronson Avenue and Percy Street.
  • Closed for 3 weekends in 2024 for the EBL approach slab construction staging at Preston Street.
  • Four (4) month closure in 2024 for retaining wall work.

Highway 417 WB off Ramp to Parkdale Avenue

  • Two (2) week closure in 2024 for work at the bullnose.
  • Three (3) month closure in 2025 for retaining wall work.

Parkdale Avenue on Ramp to Highway 417 WB

Closed for 5.5 months in 2025 and in conjunction with 417 E-N Island Park Drive Ramp closure for retaining wall work.